Contract awarded
GM Tschlin - Etappe 22, Weg 42, Baumeisterarbeiten
- Publication
- 28890-02
- Published
- 2026-02-12
- Procedure
- Open procedure
462’391Total CHF
2bids received
GRCanton
Award1 awardee
Koch AG Ramosch
462’391 CHF · 6 awards in the register
Contracting authority's reasons
Vorteilhaftestes Angebot unter Berücksichtigung der bekannt gegebenen Zuschlagskriterien.
Description
Weglänge 972 m; Betonplatten 1600 m²; Abtrag 650 m³; Schüttung 1200 m³; Fundationsmaterial 1500 m³; Kies 260 m³; Sickerpackung 250 m
Official publication: View project 28890 on simap.ch — only the publication there is authoritative.
Details
| Contracting authority | Kindschi indschegners e geometers SA |
|---|---|
| Canton | Graubünden |
| Contract type | Works contract |
| CPV | 45000000 Construction work |
| Covered by international treaties | No |